Ijraset Journal For Research in Applied Science and Engineering Technology
Authors: Himanshu Malunjkar, Madhura Aher
DOI Link: https://doi.org/10.22214/ijraset.2023.52668
Certificate: View Certificate
The aim of this paper is to propose and recommend a tool for contractors before the bidding stage to calculate the effect of delay in road construction projects by finding the relative importance index (RII) method. Through a rigorous literature search and interviews with road construction professionals, 95 delay causes were discovered and classified into 9 broad groups for this purpose. The relative importance index approach was used to calculate the relative relevance of delay factors and groups. The ranking of these factors and groups were illustrated in terms of their impact on delay. The factors and groups that are most and least responsible for the delays were explored.
I. INTRODUCTION
Construction industry is the second vital economic sector after agriculture that plays crucial role in social and economic development of India. Construction industry plays an important character in the social, economic, and political development of a country. Construction projects are time bounded. Each project has destined duration with defined initiating and completion time. Poor cost management and overrun are the huge problems and a veritably serious issue when they come to project time and cost in both developed and developing countries. In many different construction projects, delays are prevalent and can result in significant losses for project participants. The construction industry has a veritably poor reputation for managing delays. Delay analysis is either ignored or carried out subjectively by simply adding a contingency. As a result, numerous major projects fail to meet schedule deadlines. In a road construction project where time truly equals money, the management of time becomes very critical (Duran, O. (2006)), thus predicting the likelihood of delay might play a key role towards project success (Luu, et al. (2009). Delay means non-completion of the project within the prescribed duration agreed on contract. According to Kaming (1997), delay is the extended time beyond planned completion dates by the contractors during the contract. Elinwa (2001) defined delay as the period between the agreed completion data and the actual data of completion. Trigunarsyah, B. (2004) identified that only 47% of the projects in Indonesia were completed on schedule, 15% before scheduled time, and 38% were delayed.
A. Need of the Study
In India, the road construction industry constitutes a very high percentage of the economy contract. Nevertheless, quite few studies have adopted the use of project management approaches to manage the delays. A significant factor which contributes to this problem is lack of application of project management approaches to tackle these delays. This has resulted in poor quality of works, loss of productivity, delayed projects’ completion, and increase of total cost of project, unemployment, liquidation of construction firms, disputes, and litigations.
???????B. Objectives
II. REVIEW OF LITERATURE
Some theoretical and analytical investigations performed in this field are presented in the following literature survey.
III. METHODOLOGY
This section introduces the methodology used in this study to accomplish the study’s objectives. Basically, this research work includes four different phases. First phase of research covers review of literatures. Second phase of research includes development of framework of collected data for the ranking of delay in road construction projects. Third phase of research includes analysis of collected data and discussion on the comparing the result of ranking by RII technique. Here, relative importance index (RII) is calculated for each cause by using 5 likert ranking scale based on the questionnaire survey obtained from respondents of different construction companies in India.
RII = ∑W / (A x N) ……………… (1)
Where, W = weights given to each factor by the respondents (ranges from 1 to 5 relating 1 as very less severe and 5 as very high severe), A = highest weight in the rating scale (i.e., 5 in this case) and N = total number of responses. Fourth phase of research covers conclusion and recommendation part.
The data obtained from different personnel survey consists a total of 123 samples/ responses were obtained from questionnaire survey. Out of these, 16 responses were received from Project Owner, 24 responses from Contractors, 30 responses from Project Managers, 39 responses from Project Engineers/ Site Engineers and 14 responses from Consultant/ Architect.
TABLE I shows tabular list of delay factors according to their related group and their respective RII along with ranking of the listed factors.
IV. RESULTS ANALYSIS AND DISCUSSIONS
TABLE I shows tabular list of delay factors according to their related group and their respective RII along with ranking of the listed factors.
TABLE I List Of Delay Causes, Their Related Group, Rii And Ranking Of Each Factor
Sr. No. |
Main Group |
Factors |
RII |
Individual Category Rank |
Overall Rank |
|
1. |
Project Owner related factors |
1. |
Change of scope order during construction |
0.63 |
5 |
8th |
2. |
Conflicts between joint ownership of the project |
0.29 |
16 |
84th |
||
3. |
Late in approval design document by the owner |
0.72 |
2 |
2nd |
||
4. |
Delay in progress payment by the owner |
0.62 |
6 |
10th |
||
5. |
Owner’s failure to furnish and deliver the site to the contractor on time |
0.30 |
14 |
79th |
||
6. |
Improper feasibility study before project design |
0.32 |
13 |
73th |
||
7. |
Poor owner’s representative |
0.33 |
12 |
67th |
||
8. |
Lack of owner experience in construction projects |
0.36 |
11 |
57th |
||
9. |
Unavailability of incentives to the contractor for finishing ahead of schedule |
0.28 |
17 |
87th |
||
10. |
Poor communication and coordination between consultant and owner |
0.42 |
8 |
46th |
||
11. |
Decision-making process is too slow |
0.30 |
15 |
80th |
||
12. |
Suspension of work by owner |
0.24 |
18 |
95th |
||
13. |
Inadequate planning |
0.64 |
4 |
6th |
||
14. |
Inappropriate contractual procedure |
0.46 |
7 |
32nd |
||
15. |
Land Acquisition |
0.74 |
1 |
1st |
||
16. |
Delay in approving shop drawings and sample material |
0.71 |
3 |
3rd |
||
17. |
Selecting inappropriate contractors |
0.38 |
10 |
55th |
||
18. |
Changing specifications of material after project progress is started |
0.39 |
9 |
52nd |
||
2. |
Contractor related factors |
19. |
Subcontractors are frequently changed because of their poor performance |
0.41 |
7 |
49th |
20. |
Less experience of the contractor |
0.42 |
5 |
47th |
||
21. |
Improper construction method implemented by contractor |
0.42 |
6 |
48th |
||
22. |
Incompetent project team |
0.34 |
10 |
66th |
||
23. |
Ineffective project planning and scheduling |
0.55 |
1 |
19th |
||
24. |
Poor communication and coordination between contractor and consultant |
0.43 |
4 |
44th |
||
25. |
Poor site management and supervision |
0.37 |
9 |
56th |
||
26. |
Rework due to errors |
0.28 |
12 |
88th |
||
27. |
Unreliable subcontractors |
0.32 |
11 |
74th |
||
28. |
Inadequate site investigation |
0.41 |
8 |
50th |
||
29. |
Inappropriate contractor’s policies |
0.44 |
3 |
37th |
||
30. |
Poor financial control on site |
0.53 |
2 |
23rd |
||
3. |
Consultants/ Architects related factors |
31. |
Inadequate experience of consultant |
0.44 |
2 |
38th |
32. |
Conflict between consultant and design engineer |
0.33 |
5 |
68th |
||
33. |
Delay in approving major changes in the scope of work by consultant |
0.56 |
1 |
16th |
||
34. |
Delay in performing inspection and testing by consultant |
0.29 |
8 |
85th |
||
35. |
Inaccurate site investigation |
0.30 |
7 |
81st |
||
36. |
Inadequate Project Management assistance |
0.32 |
6 |
75th |
||
37. |
Late in reviewing and approving design documents |
0.36 |
4 |
58th |
||
38. |
Poor communication between consultant and others |
0.43 |
3 |
45th |
||
4. |
Design related factors |
39. |
Complexity of project design |
0.53 |
1 |
24th |
40. |
Design changes by owner or his agent during construction |
0.51 |
2 |
25th |
||
41. |
Design errors and omissions made by designers |
0.33 |
6 |
69th |
||
42. |
Insufficient data collection and survey before design |
0.44 |
3 |
39th |
||
43. |
Lack of design team experience in construction projects |
0.41 |
5 |
51st |
||
44. |
Mistakes and delays in producing design document |
0.33 |
7 |
70th |
||
45. |
Misunderstanding of owner’s requirements by design engineer |
0.28 |
10 |
89th |
||
46. |
Poor use of advanced engineering design software |
0.27 |
11 |
93rd |
||
47. |
Unclear and inadequate details in drawings |
0.32 |
8 |
76th |
||
48. |
Incomplete project design |
0.44 |
4 |
40th |
||
49. |
Defective design made by designers |
0.30 |
9 |
82nd |
||
5. |
Project related factors |
50. |
Complexity of project (project type, etc.) |
0.39 |
2 |
53rd |
51. |
Original contract duration is too short |
0.44 |
1 |
41st |
||
52. |
Ineffective delay penalties |
0.28 |
5 |
90th |
||
53. |
Legal disputes between the project participants |
0.30 |
4 |
83rd |
||
54. |
Unfavorable contract clauses |
0.33 |
3 |
71st |
||
6. |
Material related factors |
55. |
Damage of sorted materials |
0.51 |
5 |
26th |
56. |
Delay in manufacturing materials |
0.49 |
6 |
28th |
||
57. |
Changes in material types and specifications during construction |
0.45 |
7 |
33rd |
||
58. |
Escalation of material prices |
0.62 |
3 |
11th |
||
59. |
Late delivery of materials |
0.63 |
2 |
9th |
||
60. |
Late procurement of construction materials |
0.66 |
1 |
5th |
||
61. |
Poor quality of construction materials |
0.35 |
9 |
63rd |
||
62. |
Shortage of construction materials |
0.60 |
4 |
12th |
||
63. |
Unreliable suppliers |
0.36 |
8 |
59th |
||
7. |
Labor related factors |
64. |
Absenteeism of labors |
0.45 |
4 |
34th |
65. |
Low productivity level of labor |
0.54 |
2 |
21st |
||
66. |
Personal conflicts among labor |
0.35 |
6 |
64th |
||
67. |
Shortage of skilled labor |
0.49 |
3 |
29th |
||
68. |
Slow mobilization of labor |
0.32 |
7 |
77th |
||
69. |
Labor strikes |
0.55 |
1 |
20th |
||
70. |
Unqualified/Inadequate experienced labor |
0.39 |
5 |
54th |
||
71. |
Labor injuries at site |
0.28 |
8 |
91st |
||
8. |
Plants, Machinery and Equipment related factors |
72. |
Equipment allocation problem |
0.44 |
6 |
42nd |
73. |
Machinery/Equipment/Plant breakdown |
0.50 |
3 |
27th |
||
74. |
Shortage of machinery and equipment |
0.70 |
1 |
4th |
||
75. |
Availability of machinery and equipment |
0.45 |
5 |
35th |
||
76. |
Low productivity and efficiency of the equipment |
0.54 |
2 |
22nd |
||
77. |
Lack of high technology mechanical equipment |
0.36 |
7 |
60th |
||
78. |
Unskilled equipment operator |
0.47 |
4 |
30th |
||
9. |
External related factors |
79. |
Accidents during construction |
0.58 |
3 |
14th |
80. |
Changes in government regulation and law |
0.60 |
2 |
13th |
||
81. |
Delay in obtaining Permits of plants |
0.57 |
4 |
15th |
||
82. |
Forest and Environment Clearances from Municipality/Authority |
0.56 |
5 |
17th |
||
83. |
Delay in performing final inspection by third party |
0.28 |
16 |
92nd |
||
84. |
Late certification from third party |
0.45 |
8 |
36th |
||
85. |
Unavailability of utilities at site (water, electricity, telephone) |
0.56 |
6 |
18th |
||
86. |
Global financial crisis |
0.29 |
15 |
86th |
||
87. |
Loss of time by traffic control and restriction at job site |
0.26 |
17 |
94th |
||
88. |
Price fluctuations |
0.47 |
7 |
31st |
||
89. |
Problem with neighbors |
0.35 |
12 |
65th |
||
90. |
Slow site clearance |
0.36 |
10 |
61st |
||
91. |
Unexpected surface and subsurface conditions (soil, water table, etc.) |
0.44 |
9 |
43rd |
||
92. |
Unexpected natural disasters/calamities |
0.36 |
11 |
62nd |
||
93. |
Unfavorable weather conditions |
0.64 |
1 |
7th |
||
94. |
Inappropriate government policies |
0.33 |
13 |
72nd |
||
95. |
Thefts at site |
0.32 |
14 |
78th |
In TABLE I above, bold items show the top ten (10) delay factors from RII ranking and italic items represent the five (5) least critical delay factors.
???????
As we can see from TABLE I, based on its degree to affect pre-planned project duration and how it can make project delay, the highest recorded value of RII rank is “Land Acquisition”, “Late in approval design document by the owner” and “Delay in approving shop drawings and sample material” with RII of 0.74, 0.72 and 0.71 respectively. Following groups show the individual group-wise critical delay factors to look upon in future.
The first objective was to identify the delay factors in road construction projects. Through detailed literature review and interview with experts from a leading Construction Companies, a total of ninety-five (95) delay factors were identified. The second objective was to quantify relative importances of delay factors and demonstrate the ranking of the factors and groups according to their importance level. Through interviews with a committee of specialists, this objective was accomplished. Using the calculated relative importance indices, all factors and groupings were sorted in order of importance/severity. According to these rankings, the most and the least significant factor and group was also accomplished. The third objective was to address the most contributing factors and groups to cause. This objective is shown above in Fig. 2 and below Fig. 2. The highest RII (0.519) for the groups was found as “Material related delay factors” and least RII (0.348) was for “Project related delay factors.” For each group, the three (3) most contributing factors to cause delay were presented.
[1] D. Daba and Dr. J. Pitroda, “Assessment of delay of building construction project in Vadodara City”, International Journal of Creative Research Thoughts (IJCRT), Vol. 6, Issue 2, pp. 211 - 224, 2018. [2] S. Desai and R. Purohit, “Investigation on Causes of Delays in Residential Building Construction Project”, International Research Journal of Engineering and Technology (IRJET), Vol. 9, Issue 7, pp. 1736 - 1745, 2022. [3] W. Paray and C. Kumar, “Delay Analysis in Construction Projects”, International Research Journal of Engineering and Technology (IRJET), Vol. 7, Issue 10, pp. 477 - 479, 2020. [4] S. Kadu, R. Narwade and Dr. K. Nagarajan, “An Arithmetical Approach for Ranking of Factors Impacting the Timeline of Railway Project Using Relative Importance Index Method (RII), and Important Index (IMPI)”, Strad Research, Vol. 8, Issue 7, pp. 138 - 148, 2021. [5] H. Abdelrassoul and Dr. Z. Rahim, “Delay Impact of COVID-19 Pandemic on Malaysian’s Oil and Gas Projects”, International Journal of Innovative Research in Engineering and Multidisciplinary Physical Sciences (IJIRMPS), Vol. 9, Issue 4, pp. 40 - 65, 2021. [6] A. Tayade, P. Mahatme and S. Sabihuddin, “Delay in bridge Construction and analysis by RII method”, International Research Journal of Engineering and Technology (IRJET), Vol. 7, Issue 7, pp. 2040 - 2048, 2020. [7] M. Shikalgar, K. Ravi and S. Patil, “Analysis of Material Wastage and Time Overruns in Construction Project Using Descriptive and Inferential Statistics”, International Journal of Innovative Research in Science, Engineering and Technology (IJIRSET) Vol. 7, Issue 5, pp. 5234 - 5242, 2018. [8] B. Zarei, H. Sharifi and Y. Chaghouee, “Delay Causes Analysis in complex construction projects: a Semantic Network Analysis approach”, CORE, pp. 1 - 27, 2020. [9] M. Rajgor, C. Paresh, D. Patel, C. Panchal, and D. Bhavsar, “RII and IMPI: Effective Techniques for Finding Delay in Construction Project”, International Research Journal of Engineering and Technology (IRJET), Vol. 3, Issue 1, pp. 1173 - 1177, 2016. [10] S. Jaiswal and S. Kshirsagar, “Review Paper of Factors Affecting Cost Overrun in Real Estate Industry in India”, International Research Journal of Modernization in Engineering Technology and Science (IRJMETS), Vol. 2, Issue 4, pp. 1238 - 1240, 2020. [11] M. Desai and R. Bhatt, “Critical Causes of Delay in Residential Construction Projects: Case Study of Central Gujarat Region of India”, International Journal of Engineering Trends and Technology (IJETT), Vol. 4, Issue 4, pp. 762 - 768, 2013. [12] V. Meena and S. Babu, “Study on Time Delay Analysis for Construction Project Delay Analysis”, International Journal of Engineering Research and Technology (IJERT), Vol. 4, Issue 3, pp. 1076 - 1083, 2015. [13] A. Ejem, D. Dike, L. Njoku, U. Onwuka, C. Igboanusi and U. Moneke, “Analysis of Factors of Delay in Road Construction and Other Projects in IMO State”, International Journal of Engineering Sciences and Research Technology (IJESRT), Vol. 6, Issue 12, pp. 454 - 460, 2017. [14] MoSPI, https://www.mospi.gov.in/project-monitoring.
Copyright © 2023 Himanshu Malunjkar, Madhura Aher. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Paper Id : IJRASET52668
Publish Date : 2023-05-21
ISSN : 2321-9653
Publisher Name : IJRASET
DOI Link : Click Here