Ijraset Journal For Research in Applied Science and Engineering Technology
Authors: Asnake Getu Teshome , Prashant Kumar Gangwar
DOI Link: https://doi.org/10.22214/ijraset.2022.47075
Certificate: View Certificate
Public building construction projects have become a growing concern because they ensure the construction of hospitals, colleges, offices, universities, and other public buildings to overcome social issues. However, the Ethiopian building project\'s price adjustment provision was not properly implemented. The expected programs and uses of public building construction projects are hampered. Thus, this paper is aimed to establish a mitigation measures system to a prune problem at the grass route level to solve inappropriate price adjustment clause implementation. Focused group discussion, case study, and questioner survey are employed as data-gathering instruments in this study. In addition, the study was analyzed with the use of statistical package software and the Relative Importance Index, therefore, the results confirmed good decision making at the right time, a special contract condition must be drafted by experienced professionals, value engineering of alternate materials, paying the contractor in full advance, and regular cost monitoring is identified as mitigation steps for these issues. This research addresses how we can mitigate the issue of price adjustment clause misapplication in our country. More studies in more zones and regions are required to exert positive stresses so that the study\'s findings can be used to strengthen the national conditions of contract.
I. INTRODUCTION
The construction sector plays a vital role in short-term trends, annual and more frequent growth, not just for the construction industry but also for all economic activities. Construction activity adds significantly to the country's total activity, at least in terms of the need for materials and labor inputs. The changes in construction activity tend to exacerbate and drive the economy's broader movements. Ethiopia's construction industry is afflicted by a series of difficulties that threaten to impede efforts to expand the sector. These difficulties are generally related to material shortages and market price volatility for construction materials (Mossa, 2013). According to ADB, (2018) a price adjustment is a change to the overall price of a contract to account for acceptable changes in the contract's performance costs. These provisions are planned during the planning and bid preparation stages of the procurement cycle, and they are employed as needed during the contract execution stage. Price change provisions are intended to safeguard the contractor from price hikes. The cumulative consequences of price escalation might be significant in contracts with longer delivery and completion durations. Large contracts involving price-sensitive materials or goods may see significant price rises. Price adjustments may pass on savings to the borrower as a result of downward price changes (or grant recipient). Borrowers may be tempted to shift the risk of variable input costs to contractors, but this usually comes at a higher overall cost (Mulugeta, 2018).
(Abdulkadir & Mohammed et al, 2020) found that construction cost escalation is a common concern in the construction industry, with constant increases in project costs causing major problems with the efficacy of works contracts and their performance in construction projects. Many infrastructure projects are currently being late for various reasons, and as a result, cost inflation has an impact on the project's budgeted cost. Project costs are a major issue for both owners and contractors in any type of building project. Budgeting for cost escalation is critical during the planning stage of these projects (Muleyl & Purushottam Dange, 2018).
A construction contract, by definition, is a legally binding agreement between two parties to assign the issue, the duties, the responsibilities, and the liabilities involved with the contract's performance. Because it is such a complicated type of contract that usually necessitates a lengthy tendering and negotiation process, terminating it is never an easy decision; employers often hesitate to do so even when the contractor has broken the contract; the reason for this is that it is far too difficult to begin the process of tendering for a new contractor and going through the entire process again. Employers are always hesitant since it is such a difficult decision (Bakey, 2018).
The goal of this research is to build a mitigation measures framework for Ethiopian construction to overcome erroneous price adjustment clause implementation. Furthermore, these clauses are not clear, effective, or have an easily accessible index to address this issue, preventing the project from being halted for months or years owing to a change in the master timetable.
II. OBJECTIVE
The study's main purpose is to build a mitigation measures framework for Ethiopian construction to overcome erroneous price adjustment clause implementation.
A. General Objective
The goal of this study is to establish price adjustment problem mitigation approaches to construct a framework for dealing with price adjustment.
B. Specific Objectives
C. Scope and Limitation of the Study
This study focuses on IIPAC in the public building construction projects particularly in Arsi Zone
D. Limitations of the Study
A. Sampling Technique Used
Stratified random sampling methods were used to select the research population from the three major stakeholders (client, consultant, and contractor), the regulatory body and financial institutions from Arsi Zone
This sampling method is used Because of:
B. Data Collection Techniques
All methods have short comings (Mulugeta,2018)
IV. METHOD OF DATA ANALYSIS
A. Factor Analysis
Factor analysis in SPSS (using principal component analysis) software was used to extract factors to reduce its no from 40 factors to minimum.
B. Fishbone Route Cause Analysis
Used to determining whether the causing variable retained from factor analysis is
C. Method of Data Presentation
The Data Analysis result should be presented in the form of diagrams, tables and graphs, therefore:
a. Frequency Tables and Graphs
b. Table, Different types of bar charts
D. Reliability
This research is thought to be trustworthy. Cronbach's alpha, the internal consistency of the between-item scale, is used to assess its reliability.
A. Criticizing Frame work and Implications of the Study
This framework criticized and accepted by:
a. Consultants: ECO,KULCE,AZUHD Engineers
b. Contractors: ABDI construction PLC-G-1,Girma G/S B.C G-2
c. Client Side: AZEO,AZHO Engineers and regulatory body
B. Theoretical Implications
The researcher added new variables on theory so that it could cover wider perspectives.
C. Practical Implications
The research result used to mitigate the hot issue facing the industry fore going currently.
A. Based On The Study We Can Finally Come To The Following Conclusion 1) (3C’s) and regulatory body understand, recognize and work on these identified changes in price. 2) Practicing bid contingency cost, increasing the client awareness, continuous cost database, conducting regular market assessments are good practice to solve PA practice problems. 3) Including the issue of the price adjustment clause by bringing up the national rate adjustment as part of the contract document are good solutions to reduce its impact. 4) working together to overcome the poor implementation of the price adjustment clause with corresponding stakes, and assigning the right person to the right position can solve the problem B. Recommendations 1) 3C’s and the regulatory body should play their role to work with banks, suppliers, and factories collaboratively to reduce price escalation issues. 2) The regulatory body should advise the government to minimize the challenges of price adjustment practice 3) making price escalation indexes as a part of the contract document to alleviate the impacts of price adjustment problems 4) The construction sector should be administered and managed by engineering professionals to solve the price adjustment issues early.
[1] (Alinaitwe, Apolot et al, 2013). (2013). Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects. 26pp. [2] ADB. (2018). Price Adjustment Guidance Note on Procurement (p. 26pp). [3] Ahmad, N. A. et al. (2019). Cost Overruns on Federal Capital Territory Authority Road Construction Projects. FUTY Journal of the Environment, 13(1), 1–14. [4] Alves, T. et al. (2018). Construction Research Congress 2018. Proceeding of Construction Research Congress 2018, 1996(BuildingSMART 2007), 148–157. https://ascelibrary.org/doi/pdf/10.1061/9780784481301 [5] Bakey. (2015). Termination Construction Contract and The Relate. July. [6] Dadi. (2017). Adama Science and Technology University School of Architectural and Civil Engineering Department of Civil Engineering. April. [7] Data. (2011). Challenges Facing the Construction Industry in Developing Countries. Journal of Civil Engineering, 29–30. http://www.culi.chula.ac.th/e-Journal/bod/Suphat Sukamolson.pdf%5Cnhttp://isites.harvard.edu/fs/docs/icb.topic1463827.files/2007_Sukamolson_Fundamentals of Quantitative Research.pdf [8] Earl, J. et. a. (2010). Best Practices for Dealing with Price Volatility in Utah Commercial Construction. [9] Eleyan. (2018). Factors Affecting Cost Escalation in Construction Project in Gaza Strip. December, 121. [10] Emiru. (2016). Contract Price Adjustment in Ethiopian Construction Industry Misconceptions and Antidotes. From MoWUD1994 to PPA 2011 condition differently. Price adjustment methods have their own inherent limitations. contractprovisions addtheir own adjustment is put in (Issue 4). [11] ENR. (2004). For Fabricator, Steel Price Hike Helped Turn Out The Lights: Interstate Iron Works’ Liquidation Puts Big New York Job In Limbo, Engineering News- Record, p. 26, March 21 ?. 26pp. [12] Ferede. (2017). Addis Ababa Science and Technology University School of Graduate Studies College of Architecture and Civil Engineering Department of Civil Engineering Claims and Disputes Regulation and Management under the MDB- FIDIC ( 2006 ) and PPA ( 2011 ) Condition o. June. [13] Francis), (Taylor &. (2015). Cost Escalation, Schedule Overruns and Quality Shortfalls on Construction Projects: The Case of Zambia. American Journal of Applied Sciences, 50–51. [14] Gebeyehu, Submitted, T., Presented, E. E., & Fulfillment, P. (2017). Review on Price Adjustment Valuation Practices in Ethiopian Federal Road Construction Projects. [15] Hailu, Mollaw, M., & Al., E. (2015). : Causes of Price Escalation and Its Impact on Construction Contractores In Ethiopia EiABC. June, 43–57. [16] Jithin, T. J., Jebestina, N., & George, S. et al. (2021). International Journal of Intellectual Advancements and Research in Engineering Computations Study and investigation of price variation in construction materials across Kerala International Journal of Intellectual Advancements and Research in Engineering C. January. [17] Kanchana, S., & Sukumaran, E. (2020). a Critical Study on Cost Escalation in Construction Industry. International Journal of Engineering Technologies and Management Research, 5(2), 194–197. https://doi.org/10.29121/ijetmr.v5.i2.2018.163 [18] Kitzinger, J. and. (1994). The methodology of Focus Groups?: the importance of interaction between research participants. 16(1). [19] Koirala and Raj. (219 C.E.). Proceedings of IOE Graduate Conference, 2019-Summer Peer Reviewed. 315–320. [20] Kothri, C. . (2004). Research Methodology Method and Technique. [21] Mohammed Ercan. (2017). Astudy on the Price Escalation System in Public Construction Contract in Turkey (p. 168). [22] Mossa, M. G. (2013). Assessment of Price Escalation and Adjustment Problems on Federal Road Construction Projects. 1–100. [23] Muleyl, S., & Purushottam Dange. (2018). “ The study on Evaluation of Cost Escalation in Infrastructure Projects & It ’ s Provisions ”. International Research Journal of Engineering and Technology (IRJE, July 2019, 2176–2180. [24] Mulugeta. (2018). Assessment of Conditions of Contract Problems in Ethiopian Construction Industry. [25] Muya. (2014). Cost Escalation, Schedule Overruns and Quality Shortfalls on Construction Projects: The Case of Zambia. International Journal of Construction Management, 66–67. [26] MUYA, K. et al. (2014). COST ESCALATION, SCHEDULE OVERRUNS AND QUALITY SHORTFALLS ON CONSTRUCTION PROJECTS: THE CASE OF ZAMBIA. The International Journal of Construction Management, Vol. 13(1), 53–68. [27] Oyieyo, P. A., Rambo, C. M., & Ndiritu, A. et al. (2020). Ranking the prevalence of construction cost overrun risk factors in completion of public-private partnership projects. International Journal of Research in Business and Social Science (2147- 4478), 9(5), 351–356. https://doi.org/10.20525/ijrbs.v9i5.863 [28] Pascal. (2020). Factors Affecting Time and Cost performance of Projects in Rwanda. 52p. [29] Pearl.R. (1997). Impacts of Absence of price adjustement clause on construction. Journal of Construction Engineering, 40–45. https://doi.org/10.1038/bdj.2008.192 [30] Rameezdeen, Palliyaguru, et al. (2018). Financing Contractors in Developing Countries: Impact of Mobilization Advance Payment, Department of Building Economics, University of Moratuwa, Sri Lanka in association with Research Institute for the Built and Human Environment, University of Salford, U. In Resource Allocation and Economic Policy (Issue June). https://doi.org/10.1007/978-1-349-02673-9_1 [31] Seneviratne, P. N. and. (n.d.). Costs and Benefits of the Price Adjustment Clause in FIDIC MDB. Costs and Benefits of the Price Adjustment Clause in FIDIC MDB. [32] Van der Schans, P. (2005). Increasing Material Prices Gouge Construction Industry,Construction Executive (pp. 26-29pp). [33] Yigezu. (2008). Study on the Effects of Unpredictable Price Fluctuation on the Capacity of Construction Contractors. Msc Thesis Addis Ababa University, Ethiopia. In RISTI - Revista Iberica de Sistemas e Tecnologias de Informacao. [34] Zegeye. (2019). Assessment of Challenges and Best Practices of Price Adjustment on Federal Road Construction Projects (Issue February).
Copyright © 2022 Asnake Getu Teshome , Prashant Kumar Gangwar. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
Paper Id : IJRASET47075
Publish Date : 2022-10-13
ISSN : 2321-9653
Publisher Name : IJRASET
DOI Link : Click Here