Authors: Avinash Rathore, Manoj Kumar Trivedi
DOI Link: https://doi.org/10.22214/ijraset.2021.39242
Certificate: View Certificate
Government has approved the hybrid annuity model (HAM) for building National Highways (NH) to speed up the construction of roads in the country by renewing interest of private developers in highway projects. 40% the Project Cost is to be provided by the Government as Construction Support during the construction period and the balance 60% as annuity payments over the operations period along with interest thereon to the concessionaire. Execution of hybrid annuity model (HAM) projects, which is the preferred mode of awarding by the National Highways Authority of India (NHAI), is largely on schedule with about 60% of projects, covering 3,200 km of roads, completed on time. The rest of the projects, however, are delayed largely due to various reasons. In order to identify and analysis of delay causes in highway projects of HAM model, this study provides a questionnaire survey-based study. Land acquisition delay is found as the most severe delay cause of highway projects of HAM model. Waste of time in controlling the traffic is found as the least severe delay cause of highway projects of HAM model. The study is supposed as useful to HAM construction managers for delay analysis of highway projects.
I. INTRODUCTION
Government has approved the hybrid annuity model (HAM) for building National Highways (NH) to speed up the construction of roads in the country by renewing interest of private developers in highway projects. 40% the Project Cost is to be provided by the Government as Construction Support during the construction period and the balance 60% as annuity payments over the operations period along with interest thereon to the concessionaire. National Highway projects worth approximately Rs 10,000 crore have been approved in this financial year (till 31.10.2019) under the hybrid annuity mode. The objective is to maximize the quantum of implemented projects within the available financial resources of the Government and to revive private sector participation in the sector. Toll fee collection from the highway projects developed under the hybrid annuity model is the responsibility of the Government/Authority. In order to tap the benefit of long-term funds like pension fund, insurance fund, wealth fund etc into road construction sector, MoRTH has introduced models like HAM and TOT (Toll-Operate-Transfer). The government has argued that as many as 210 national highway projects are delayed due to various reasons such as poor performance by developers and problems in land acquisition besides regulatory hurdles. It also said there are some hybrid annuity model (HAM) projects which are yet to secure financial closure.
"210 nos. of National Highway projects are delayed under NHAI due to various reasons. The delays are due to multiple reasons, such as poor performance of Contractors/Concessionaires, delays in various activities and clearances such as utility shifting, environment/forest clearance, land acquisition and law & order problems etc," Minister of State for Road Transport and Highways V K Singh told the Rajya Sabha in a written reply.
The steps include constitution of High-Powered Committee under Chief Secretary to monitor the pre-construction activities, strengthening of Land Acquisition Units by way of providing manpower and resources and effective formal public consultations at the time of project preparation to address the concerns of public, he added. The minister added that there are some HAM projects which are yet to secure financial closure.
II. OBJECTIVES OF THE STUDY
The objectives of the study are given as follows:
III. LITERATURE REVIEW
Prathamesh Brid and Raju Narwade (2017) found that fuzzy logic approach simplize the tough job of project manager to analyze the unclear and vague data and information. They also found that fuzzy logic is useful and satisfactory approach for decision making in construction industry. Hesham Abd El Khalek, Remon Fayek Aziz, Hamada Mohamed Kamel (2016) utilized the fuzzy logic approach to liklihood and impact of risks folllowing the vagueness in the liklihood and impact of risk. They evaluate the risk in construction projects through calculating the R-index of each risk which is function of liklihood and impact of risk. John B. Bowles & C. Enrique Pelaez (1995) have concluded that FMEA & FMECA are the more effective methods than traditional methods to analyze the failures in a product or system. Bowles and Pelaez also found that involvement of fuzzy logic in FMEA technique can give more precise and accurate information about failure status of product or system. To apply fuzzy logic in FMEA, it is required to define linguistic terms, fuzzy numbers and and membership functions of risk occurrence, risk consequences, risk detectability and risk priority number. Bowles and Pelaez also conclude that fuzzy logic with FMEA is also most useful when there is lack of availability of information. Bowles and Pelaez also noted that, if failure modes have multiple dimensions, then calculated RPN might be underestimated. Mohamed Abdelgawad and Aminah Robinson Fayek (2010) found the RPN values of identified risk factors in construction industry using Fuzzy-MATLAB. They used Impact of risk, probability of occurrence of risk and current control on risk as input and RPN as output in Fuzzy-MATLAB. They applied Fuzzy-AHP to count weight of impact of risk on cost, time and quality of construction project. They also concluded that responses should be given to risk events based on RPN values prioritization not on the rules of thumb. Fuzzy and FMEA was concluded as appropriate and satisfactory to calculate RPN values of risk factors. Cheng-Min Feng and Chi-Chun Chung (2013) assessed the the risks in airport airside using fuzzy logic and FMECA. They identified 14 risk factors from the aviation accident database of International Civil Aviation Organization (ICAO). Each risk factor was considered as failure mode. They conduct a case study using questionnaire on Taiwan Taoyuan International Airport. They elicit the information from experts about probability, severity and detectability of risk factors in airport airside. RPN of each risk factor was calculated by making a fuzzy model on MATLAB software. They gave more attention to higher RPN value risk than lower RPN value risks Mohsen Ahmadi, Kouroush Behzadian, Abdollah Ardeshir and Zoran Kapelan (2015) managed the risks in construction of highway projects. They used fuzzy logic in FMEA & MCDA to assess and prioritize the risk factors. Combined fuzzy-AHP was used to compute the impact of risk factors on cost, time and quality of work. They identified 30 risk factors and calculated the RPN values of risks. Risk were prioritized on the basis on RPN value. Higher RPN risk was responded firstly. Lack of fund and time was identified most significant factors. They also conclude that suggested response strategies are sufficient, useful and appropriate to handle the risks in construction of highway projects. Sameh M. El-Sayegh and Mahmoud H. Mansour (2015) assessed and allocated risks in highway construction projects in UAE. They identified 33 risk factors and designed a questionnaire to elicit information from experts about probability of occurrence and impact of risk and risk allocation on highway construction projects. They found Risk occurrence index and Risk Impact index using Relative Importance Index (RII) method to find significant risk factors. They also differentiate the risk factors on the basis of contractors, consultants and owners views. They found strong correlation between all three groups of respondents using spearman rank correlation coefficient. They also analyzed the risk allocation suggested by owner and contractors and recommended the final risk allocation plan. Mahmoud Mohamed Mahmoud Sharaf and Hassan T. Abdelwahab (2015) analyzed the risk factors in Highway Construction Projects in Egyp using risk score. They identified the 73 risk factors and categorized them into 12 risk groups. To elicit the information for occurrence and impact of risk questionnaire method was used. They calculated the Risk Score by multiplying Average Impact and Average Probability of Occurrence, while average probability of occurrence and average impact was calculated by Relative Importance Index (RII) method. Delay in Decision making and land acquisition was found most significant risk factors based on Risk Score value. They also concluded that risk factors having high frequency of occurrence in the life cycle of project and having high impact on project’s cost and time are most risky factors in construction of highway projects of Egypt.
In literature, no study related to delay in HAM highway projects was found. Therefore, the presented study provides a detailed questionnaire survey-based delay analysis study for HAM highway projects.
IV. RESEARCH METHODOLOGY
The step-by-step methodology is given as below:
A. Step-1) Delay factors identification
Identified delay factors are shown in Table 1.
B. Step-2) Questionnaire Design
Level of severity was taken on 1-to-5-point scale. Questionnaire survey is conducted among 384 respondents.
C. Step-3) Descriptive Statistics
Relative importance index (RII) is calculated for ranking of delay factors.
D. Step-4) Ranking
Ranking is done on the basis of RII value.
V. RESULTS AND DISCUSSION
In questionnaire survey, there were 123 clients, 159 contractors and 102 consultants.
For example, Table: 2 shows the overall response of 70 respondents. For numerical example take the response of an example factor. Out of 70 respondents, 20 said that factor is very low, 13 said that factor is low, 7 said that factor is medium, 20 said that factor is high and 10 said that factor is very high. Now from crisp rating Table 2:
VI. RECOMMENDATIONS TO REDUCE THE DELAY IN HAM INDIAN HIGHWAY CONSTRUCTION PROJECTS
After analysing the results of this study, the following recommendations to address the top ten factors for delay in road construction projects:
The presented study has been provided a detail analysis of delay causing factors of HAM Indian highway construction projects. For this purpose, this study provides a questionnaire survey based detailed study over identified 35 delay causing factors. Severity of each delay factor was elicited from 384 HAM highway construction experts including 123 government/client employees, 159 concessionaire/contractor employees and 102 consultant employees. Based on the various statistical analysis such as ranking of delay factors and correlation analysis, the study illustrates following conclusions: A. The obtained value of ACP and Cronbach’s alpha was 92% and 0.973 respectively. Therefore, the data obtained from questionnaire was found as valid and reliable. B. About more than 200 HAM highway construction projects were found behind the schedule. C. Delay in land acquisition is found as the main delay causing factor of HAM Indian highway construction projects. D. PCA analysis also shows that delay in land acquisition is found as the main delay causing factor of HAM Indian highway construction projects. E. Spearman’s Coefficient of correlation shows that there was strong correlation between the responses of client, contractor and consultant data. F. Inefficient planning, scheduling and controlling of project is found as topmost contractor related delay causing factor. G. Delay in inspection of work by consultant is found as topmost consultant related delay factor. H. Weak sponsors are found as topmost project related delay factor. I. Lack of adequate skilled labours is found as topmost labour related delay factor. J. Equipment of lesser efficiency is found as topmost material and equipment related delay factor. K. Delay in design works is found as topmost design related delay factor. L. Public agitation demanding other facilities/(law and order problem) is found as topmost external delay factor. M. Delay is land acquisition is found as topmost government related delay factor.
[1] John B. Bowles & C. Enrique Pelaez ., (1995) “Fuzzy logic prioritization of failure in a system failure mode, effects and criticality analysis”. Reliability Engineering and System Safety. [2] John B. Bowles & C. Enrique Pelaez ., (2003) “An assessment of RPN prioritization in a failure mode effects and criticality analysis.” IEEE, Reliability and Maintainability Symposium. [3] Thompson, P., and Perry, J.G. (1992). Engineering Construction Risks: A guide to project risk analysis and risk management, Thomas Telford, London. [4] Bambang Purwanggono & and Anastasia Margarette., (2017) “Risk assessment of underpass infrastructure project based on ISO 31000 and ISO 21500 using fishbone diagram and RFMEA (project risk failure mode and effect analysis) method”. IOP Conference Series: Material Science and Engineering [5] Cheng-Min Feng and Chi-Chun Chung., (2013) “Assessing the risks of airport airside through the fuzzy logic-based failure modes, effect and criticality analysis”. Hindawi Publishing Corporation, Mathematical Problems in Engineering. [6] Mohamad Abdelgawad and Aminah Robinson Fayek., (2010) “Risk management in the construction industry using combined Fuzzy FMEA and Fuzzy AHP”. Journal of Construction Engineering and Management. [7] Sameh M. El-Sayegh and Mahmoud H. Mansour., (2015) “Risk Assessment and allocation in Highway Construction projects in the UAE”. Journal of Management in Engineering. [8] Mohammad Hayati and Mohammad Reza Abroshan., (2017) “Risk Assessment using Fuzzy (Case Study: Tehran Subway Tunneling)” Indian journal of Science and Technology. [9] Maryam Gallab, Hafida Bouloiz, Youssef Lamrani Alaoui, Mohammad Tliouat., (2018) “Risk Assessment of Maintenance activities using Fuzzy Logic” Procedia Computer Science. [10] Mahmoud Mohamed Mahmoud Sharaf and Hassan T. Abdelwahab., (2015) “Analysis of Risk Factors for Highway Construction Projects in Egypt”. Journal of Civil Engineering and Architecture. [11] Mohsen AHMAD, Kourosh BEHZADIAN, Abdollah ARDESHIR, Zoran KAPELAN., (2015) “Comprehensive Risk Management using Fuzzy-FMEA and MCDA Techniques in Highway Construction Projects”. Journal of Civil Engineering In Management. [12] Hesham Abd El Khalek, Remon Fayek Aziz, Hamada Mohamed Kamel., (2016) “Risk and Uncertainty Model in Construction Projects Using Fuzzy Logic”. Journal of Construction Engineering and Management. [13] Hesham Abd El Khalek, Remon Fayek Aziz, Hamada Mohamed Kamel., (2016) “Risk and Uncertainty Assessment Model in Construction Projects Using Fuzzy Logic”. American Journal of Civil Engineering. [14] Prathamesh Brid and Raju Narwade., (2017) “Fuzzy Logic Used for Decision Making in Construction Industry”. International Journal on Recent and Innovation Trends in Computing and Communication. [15] S. Rajasekaran and G.A. Vijayalakshmi Pai., Book “Neural Networks, Fuzzy Systems and Evolutionary Algorithms” [16] Ali Akbari Ahmadabadi and Gholamreza Heravi., (2019) “Risk Assessment Framework of PPP-megaprojects focusing on risk interaction and project success”. Transportation Research Part A, Elsevier. [17] Remon Fayek Aziz Eskander., (2018) “Risk Assessment Influencing factors for Arbian Construction Projects Using Analytical Hierarchy process”. Alexandria Engineering Journal, Elsevier. [18] Pawel Szymanski., (2017) “Risk management in construction project” 2nd International Conference on Innovative Solutions in Construction Engineering and Management.
Copyright © 2022 Avinash Rathore, Manoj Kumar Trivedi. This is an open access article distributed under the Creative Commons Attribution License, which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.